You are configuring a SharePoint farm. You have the following requirements:

✑ Implement an enterprise resource pool.
✑ Enable tasks to be assigned to users.
✑ Implement a resource breakdown structure.
You need to implement a solution that meets the requirements. What should you do?

A. Create a SharePoint task list.
B. Integrate Microsoft Project Server with SharePoint.
C. Create a SharePoint team site.
D. Create a collaboration portal.