You are using Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development. You have the following requirements: ✑ All work and progress on individual projects must be reflected in the e-commerce portal development program. Each group must be able to manage their own tasks. You need to set up the e-commerce portal development program and its associated projects in Microsoft PPM. Where should you add resources?

A. in the e-commerce portal development program project site
B. in the individual project schedules
C. in Build Team, in the e-commerce portal development program schedule
D. in the individual project sites